All Projects

DXB AIRPORT EXPANSION PHASE 3 (CARGO MEGA TERMINAL), UPGRADE AND EXPANSION OF MATERIAL HANDLING SYSTEM
Our Role
E & I Sub Contractor
End User
Dubai International Airport
Job Carried Out
Installation, Pre-commissioning & Commissioning for Electrical & Instrumentation
Metromac as a subcontractor for Siemens has executed the scope with site establishment, complete electrical installation, and functional testing, and recommissioned the material handling system of the Cargo Handling System. The engineering contractor is Siemens.
PLC Panel (Siemens), Operator Station-Ray control, Scanner Control, SMDBs, and Fire Shutter Panels
Erection of ASRS, LSP, Truck Dock, Transfer Car, Transfer Vehicle, QDT, and ULD Systems
Installation of Cable Tray, Flexible & rigid Conduit, and Supports
Energy Chain Installation, Profibus, Profinet, and Fiber-optic Networking.
Power and Control Cable laying, landing, and Termination
Electrical Installation, Wiring, and Hardware check (Pre-Commissioning) of all electrical field equipment with the necessary assistance to Siemens including fault Correction.
Loop checking and Pre-commissioning