KING ABDULAZIZ INTERNATIONAL AIRPORT JEDDAH NEW CARGO TERMINAL - MATERIAL HANDLING SYSTEM

KING ABDULAZIZ INTERNATIONAL AIRPORT JEDDAH NEW CARGO TERMINAL - MATERIAL HANDLING SYSTEM

Project Overview

Our Role

E & I Sub Contractor

End User

King Abdulaziz International Airport

Job Carried Out

Jeddah New Cargo Terminal - Material Handling System

Project Description

Installation, Pre-commissioning & Commissioning for Electrical & Instrumentation with IT Networking. Metromac as a subcontractor for Siemens has executed the scope of site establishment, complete electrical & IT Network installation and functional testing, and Precommissioned material handling system of the Cargo Handling System.

Scope of Work
  • PLC Panel (Siemens), Operator Station-Ray control, Scanner Control, SMDBs, IT-Networking Panels, and Fire Shutter Panels

  • Erection of ETV, Turn Table, RA Deck, Roller Deck, Shutter Doors, and ULD Systems

  • Installation of Wireless Equipments & IT Data Points for Networking

  • Installation of Cable Tray, Flexible & rigid Conduit, and Supports

  • Power / Data Feed Rail Installation, Profibus, Profinet, and Fiber-optic Networking.

  • Power and Control Cable laying, Glanding, and Termination

  • Electrical Installation, Wiring, and Hardware check (Pre-Commissioning) of all electrical field equipment with the necessary assistance to Siemens including fault Correction

  • Loop checking and Pre-commissioning